§ 16441. Funding new interconnection and transmission upgrades
Latest version.
-
The Commission may approve a participant funding plan that allocates costs related to transmission upgrades or new generator interconnection, without regard to whether an applicant is a member of a Commission-approved Transmission Organization, if the plan results in rates that— (1) are just and reasonable; (2) are not unduly discriminatory or preferential; and (3) are otherwise consistent with sections 824d and 824e of title 16.