United States Code (Last Updated: May 24, 2014) |
Title 41. PUBLIC CONTRACTS |
SubTitle III. Contract Disputes |
Chapter 71. CONTRACT DISPUTES |
§ 7109. Interest
-
(a) Period.— (1) In general.— Interest on an amount found due a contractor on a claim shall be paid to the contractor for the period beginning with the date the contracting officer receives the contractor’s claim, pursuant to section 7103(a) of this title, until the date of payment of the claim. (2) Defective certification.— On a claim for which the certification under section 7103(b)(1) of this title is found to be defective, any interest due under this section shall be paid for the period beginning with the date the contracting officer initially receives the contractor’s claim until the date of payment of the claim. (b) Rate.— Interest shall accrue and be paid at a rate which the Secretary of the Treasury shall specify as applicable for each successive 6-month period. The rate shall be determined by the Secretary of the Treasury taking into consideration current private commercial rates of interest for new loans maturing in approximately 5 years.
Historical And Revision
Historical and Revision Notes | ||
---|---|---|
Revised Section | Source (U.S. Code) | Source (Statutes at Large) |
7109(a)(1) | 41:611 (1st sentence). | Pub. L. 95–563, § 12, Nov. 1, 1978, 92 Stat. 2389. |
7109(a)(2) | 41:611 note. | Pub. L. 102–572, title IX, § 907(a)(3), Oct. 29, 1992, 106 Stat. 4518. |
7109(b) | 41:611 (last sentence). |
In subsection (a)(2), the words “on or after the date of the enactment of this Act”, “the later of”, and “or the date of the enactment of this Act” are omitted as obsolete.
Subsection (b) is substituted for “The interest provided for in this section shall be paid at the rate established by the Secretary of the Treasury pursuant to Public Law 92–41 (85 Stat. 97) for the Renegotiation Board” to eliminate obsolete language and to codify the criteria under which the interest rate is computed. Section 2(a)(3) of the Act of July 1, 1971 (Pub. L. 92–41, 85 Stat. 97), amended section 105(b)(2) of the Renegotiation Act of 1951 (Mar. 23, 1951, ch. 15, 65 Stat. 13) by adding provisions substantially similar to those enacted here. However, the Renegotiation Act of 1951 (Mar. 23, 1951, ch. 15, 65 Stat. 7) was omitted from the Code pursuant to section 102(c)(1) of the Act (65 Stat. 8), amended several times, the last being Public Law 94–185 (89 Stat. 1061), which provided that most provisions of that Act do not apply to receipts and accruals attributable to contract performance after