§ 2340. Revision of project partnership agreement; cost sharing  


Latest version.
  • (a) Federal allocation

    Upon authorization by law of an increase in the maximum amount of Federal funds that may be allocated for a water resources project or an increase in the total cost of a water resources project authorized to be carried out by the Secretary, the Secretary shall enter into a revised partnership agreement for the project to take into account the change in Federal participation in the project.

    (b) Cost sharing

    An increase in the maximum amount of Federal funds that may be allocated for a water resources project, or an increase in the total cost of a water resources project, authorized to be carried out by the Secretary shall not affect any cost-sharing requirement applicable to the project.

    (c) Cost estimates

    The estimated Federal and non-Federal costs of water resources projects authorized to be carried out by the Secretary before, on, or after November 8, 2007, are for informational purposes only and shall not be interpreted as affecting the cost-sharing responsibilities established by law.

(Pub. L. 110–114, title II, § 2008, Nov. 8, 2007, 121 Stat. 1073.)

Codification

Codification

Section was enacted as part of the Water Resources Development Act of 2007, and not as part of the Water Resources Development Act of 1986 which comprises this chapter.

Miscellaneous

Reference to Partnership Agreement Deemed Reference to Cooperation Agreement

Reference to partnership agreement deemed to be reference to cooperation agreement, see section 2003(f)(3) of Pub. L. 110–114, set out as a note under section 1962d–5b of Title 42, The Public Health and Welfare.

“Secretary” Defined

Secretary means the Secretary of the Army, see section 2 of Pub. L. 110–114, set out as a note under section 2201 of this title.