§ 2330a. Monitoring ecosystem restoration  


Latest version.
  • (a) In general

    In conducting a feasibility study for a project (or a component of a project) for ecosystem restoration, the Secretary shall ensure that the recommended project includes, as an integral part of the project, a plan for monitoring the success of the ecosystem restoration.

    (b) Monitoring planThe monitoring plan shall—(1) include a description of the monitoring activities to be carried out, the criteria for ecosystem restoration success, and the estimated cost and duration of the monitoring; and(2) specify that the monitoring shall continue until such time as the Secretary determines that the criteria for ecosystem restoration success will be met. (c) Cost share

    For a period of 10 years from completion of construction of a project (or a component of a project) for ecosystem restoration, the Secretary shall consider the cost of carrying out the monitoring as a project cost. If the monitoring plan under subsection (b) requires monitoring beyond the 10-year period, the cost of monitoring shall be a non-Federal responsibility.

(Pub. L. 110–114, title II, § 2039, Nov. 8, 2007, 121 Stat. 1100.)

Codification

Codification

Section was enacted as part of the Water Resources Development Act of 2007, and not as part of the Water Resources Development Act of 1986 which comprises this chapter.

Miscellaneous

“Secretary” Defined

Secretary means the Secretary of the Army, see section 2 of Pub. L. 110–114, set out as a note under section 2201 of this title.