§ 2317b. Wetlands mitigation  


Latest version.
  • (1) In general

    In carrying out a water resources project that involves wetlands mitigation and that has impacts that occur within the service area of a mitigation bank, the Secretary, where appropriate, shall first consider the use of the mitigation bank if the bank contains sufficient available credits to offset the impact and the bank is approved in accordance with the Federal Guidance for the Establishment, Use and Operation of Mitigation Banks (60 Fed. Reg. 58605) or other applicable Federal law (including regulations).

    (2) Service area

    To the maximum extent practicable, the service area of the mitigation bank under paragraph (1) shall be in the same watershed as the affected habitat.

    (3) Responsibility for monitoring(A) In general

    Purchase of credits from a mitigation bank for a water resources project relieves the Secretary and the non-Federal interest from responsibility for monitoring or demonstrating mitigation success.

    (B) Applicability

    The relief of responsibility under subparagraph (A) applies only in any case in which the Secretary determines that monitoring of mitigation success is being conducted by the Secretary or by the owner or operator of the mitigation bank.

(Pub. L. 110–114, title II, § 2036(c), Nov. 8, 2007, 121 Stat. 1094.)

Codification

Codification

Section was enacted as part of the Water Resources Development Act of 2007, and not as part of the Water Resources Development Act of 1986 which comprises this chapter.

Miscellaneous

“Secretary” Defined

Secretary means the Secretary of the Army, see section 2 of Pub. L. 110–114, set out as a note under section 2201 of this title.