§ 565. Required contract terms  


Latest version.
  • (a) In General.—The Commandant shall ensure that a contract awarded or a delivery order or task order issued for an acquisition of a capability or an asset with an expected service life of 10 or more years and with a total acquisition cost that is equal to or exceeds $10,000,000 awarded or issued by the Coast Guard after the date of enactment of the Coast Guard Authorization Act of 2010—(1) provides that all certifications for an end-state capability or asset under such contract, delivery order, or task order, respectively, will be conducted by the Commandant or an independent third party, and that self-certification by a contractor or subcontractor is not allowed;(2) provides that the Commandant shall maintain the authority to establish, approve, and maintain technical requirements;(3) requires that any measurement of contractor and subcontractor performance be based on the status of all work performed, including the extent to which the work performed met all performance, cost, and schedule requirements;(4) specifies that, for the acquisition or upgrade of air, surface, or shore capabilities and assets for which compliance with TEMPEST certification is a requirement, the standard for determining such compliance will be the air, surface, or shore standard then used by the Department of the Navy for that type of capability or asset; and(5) for any contract awarded to acquire an Offshore Patrol Cutter, includes provisions specifying the service life, fatigue life, and days underway in general Atlantic and North Pacific Sea conditions, maximum range, and maximum speed the cutter will be built to achieve. (b) Prohibited Provisions.—(1) In general.—The Commandant shall ensure that any contract awarded or delivery order or task order issued by the Coast Guard after the date of enactment of the Coast Guard Authorization Act of 2010 does not include any provision allowing for equitable adjustment that is not consistent with the Federal Acquisition Regulations.(2) Extension of program.—A contract, contract modification, or award term extending a contract with a lead systems integrator—(A) may not include any minimum requirements for the purchase of a given or determinable number of specific capabilities or assets; and(B) shall be reviewed by an independent third party with expertise in acquisition management, and the results of that review shall be submitted to the appropriate congressional committees at least 60 days prior to the award of the contract, contract modification, or award term. (c) Integrated Product Teams.—Integrated product teams, and all teams that oversee integrated product teams, shall be chaired by officers, members, or employees of the Coast Guard. (d) Technical Authority.—The Commandant shall maintain or designate the technical authority to establish, approve, and maintain technical requirements. Any such designation shall be made in writing and may not be delegated to the authority of the Chief Acquisition Officer established by section 56 of this title.
(Added Pub. L. 111–281, title IV, § 402(a), Oct. 15, 2010, 124 Stat. 2936; amended Pub. L. 111–330, § 1(4), Dec. 22, 2010, 124 Stat. 3569.)

References In Text

References in Text

The date of enactment of the Coast Guard Authorization Act of 2010, referred to in subsecs. (a) and (b)(1), is the date of enactment of Pub. L. 111–281, which was approved Oct. 15, 2010.

Prior Provisions

Prior Provisions

A prior section 565, act Aug. 4, 1949, ch. 393, 63 Stat. 540, related to Public Health Service officers as court members, prior to repeal by act May 5, 1950, ch. 169, §§ 5, 14(v), 64 Stat. 145, 148, effective May 31, 1951.

Amendments

Amendments

2010—Pub. L. 111–330 amended Pub. L. 111–281, § 402(a), which enacted this section.

Effective Date Of Amendment

Effective Date of 2010 Amendment

Pub. L. 111–330, § 1, Dec. 22, 2010, 124 Stat. 3569, provided that the amendment made by section 1(4) is effective with the enactment of Pub. L. 111–281.