§ 8323. General requirements for exemptions  


Latest version.
  • (a) Use of mixtures or fluidized bed combustion not feasibleExcept in the case of an exemption under section 8322(d) of this title, the Secretary may grant a permanent exemption for a powerplant under this part only—(1) if the applicant has demonstrated that the use of a mixture of natural gas or petroleum and coal or another alternate fuel, for which an exemption under section 8322(d) of this title would be available, is not economically or technically feasible; and(2) if the Secretary has not made a finding that the use of a method of fluidized bed combustion of coal or another alternate fuel is economically and technically feasible. (b) State approval required for powerplant

    If the appropriate State regulatory authority has not approved a powerplant for which a petition has been filed, such exemption, to the extent it applies to the prohibition under section 8311 of this title against construction without the capability of using coal or another alternate fuel, shall not take effect until all approvals required by such State regulatory authority which relate to construction have been obtained.

    (c) No alternative power supply in the case of a powerplant(1) Except in the case of an exemption under section 8322(c) of this title, the Secretary may not grant an exemption for a new powerplant unless he finds that the petitioner has demonstrated that there is no alternative supply of electric power which is available within a reasonable distance at a reasonable cost without impairing short-run or long-run reliability of service and which can be obtained by the petitioner, despite reasonable good faith efforts.(2) The Secretary shall forward a copy of any such petition to the Federal Energy Regulatory Commission promptly after it is filed with the Secretary and shall consult with such Commission before making any finding on such petition under paragraph (1).
(Pub. L. 95–620, title II, § 213, Nov. 9, 1978, 92 Stat. 3304; Pub. L. 100–42, § 1(c)(7), May 21, 1987, 101 Stat. 312.)

Amendments

Amendments

1987—Subsec. (a). Pub. L. 100–42, § 1(c)(7)(A), (B), in introductory provisions struck out “or (g)” after “8322(d)” and “or installation” after “powerplant”.

Subsec. (b). Pub. L. 100–42, § 1(c)(7)(C), amended subsec. (b) generally. Prior to amendment, subsec. (b) read as follows: “If the appropriate State regulatory authority has not approved a powerplant for which a petition has been filed, such exemption—

“(1) to the extent it applies to the prohibition under section 8311(2) of this title against construction without the capability of using coal or another alternate fuel, shall not take effect until all approvals required by such State regulatory authority which relate to construction have been obtained; and

“(2) to the extent it applies to the prohibition under section 8311(1) of this title against the use of natural gas or petroleum as a primary energy source, shall not take effect until all approvals required by such State regulatory authority which relate to construction or operation have been obtained.”

Subsec. (c)(1). Pub. L. 100–42, § 1(c)(7)(A), in introductory provisions struck out “or (g)” after “section 8322(c)”.

Miscellaneous

Exemption for Certain Electric Powerplants as Effective Prior to 180 Days After November 9, 1978

For effectiveness of exemption for certain electric powerplants as prior to 180 days after Nov. 9, 1978, see section 902(a) of Pub. L. 95–620, set out as a note under section 8301 of this title.