United States Code (Last Updated: May 24, 2014) |
Title 16. CONSERVATION |
Chapter 12A. TENNESSEE VALLEY AUTHORITY |
§ 831o. Completion of unfinished plants authorized
-
The Board, whenever the President deems it advisable, is empowered and directed to complete Dam Numbered 2 at Muscle Shoals, Alabama, and the steam plant at nitrate plant numbered 2, in the vicinity of Muscle Shoals, by installing in Dam Numbered 2 the additional power units according to the plans and specifications of said dam, and the additional power unit in the steam plant at nitrate plant numbered 2.
Amendments
2004—Pub. L. 108–447 substituted “Board” for “board”.
Effective Date Of Amendment
Amendment by Pub. L. 108–447 effective on the later of the date on which at least three persons nominated under section 604(a) of Pub. L. 108–447 take office or